| Burj Dubai Lake & Fountain Program |
|
|
| Burj Dubai Lake, January, 2009 |
|
An area of 20,000 square meters of the lake was previously used as a temporary lake to capture storm water runoff and had been subjected to bacterial growth. These areas were cleaned to remove bacterial growth and then treated with X-Treat Sanitizer to sanitize the surface of the concrete to prevent future bacterial growth. Surface preparation was completed using a captive blasting technique. Six captive blast teams were able to prepare 6000m2 of concrete surface per day. This process produced a lightly exposed aggregate finish that revealed all the bug holes (blow holes). X-Shield Bug Fill, a two component high-build thixotropic epoxy resin, was used to fill bug-holes and surface imperfections prior to coating the lake bed.
|
 |
| Fountain Waterproofing, Westin Diplomat Hotel |
|
|
| Hollywood FL USA, October, 2007 |
|
Only 4 years old and a central feature of the prestigious Westin
Diplomat Hotel, the group of 3 fountains was discovered to be leaking
water into the foyer and below ground parking area. The fountain
constructed from concrete was originally coated with an epoxy coating
which was showing signs of cracking and delamination. As these
fountains were located in the central reception area of a very busy hotel
any remedial work had to be carried out quickly with minimal disruption
to guests. The need was for a lining system that would cure quickly
allowing quick return to service, flexible UV and chemical resistant and
could function under full immersion.
|
 |
| Renovation of Hotel Roof |
|
|
| Radisson Hotel: Nashville Airport, April, 2006 |
|
Existing roofing system was an 18 year old 24000 ft2 PVC fully adhered
membrane roof. The PVC was showing signs of weathering and needed
some patching to stop leaks. There were also flat areas on the roof
where ponded water would collect. Under new ownership and as part of
the overall refurbishment of the hotel, it was decided to recoat the roof
to extend the working life. The problem was finding a roofing system
that would adhere to the PVC and that would also handle ponded water.
|
 |
| Rawmat HDB - Waterproofing Case History |
|
|
| 717 Atlantic Avenue Elevator Pit, Boston, January, 2006 |
|
The elevator pit needed to be deepened to satisfy building codes. The elevator shaft
was also prone to frequent flooding due to the high water table. Geotechnical investigation
identified Perchloroethlene (Perc) in the ground. Perc is extremely volatile and classified by
the EPA as a Class1 carcinogen. Perc is a strong solvent and very aggressive to most waterproofing
materials. The problem was finding a waterproofing system that would resist Perc.
Under the direction of Environmental Consultant GZA, contaminated water was collected and
used to test Rawmat HDB membrane to prove that the product would be resistant to the Perc
contaminated into system.
|
 |
| Reflecting Pond, 3M World HQ |
|
|
| St Paul MN USA, October, 2005 |
|
Originally built in the late 1960s, this Reflecting Pond was lined with asphalt
and contained 3ft deep water. Due to the harsh Minnesota winters the
pond only held water for 6 months of the year (May-Sept). Over time, the
asphalt substrate had cracked and it was costing the owners $30,000 to
$40,000 per year to keep the pond watertight. The need was for a lining
system that could waterproof the aged and cracked substrate and also
withstand the 6 months wet and 6 months dry UV exposure for many years
with out cracking.
|
 |
| Renovation of Hotel Roof |
|
|
| Howard Johnson Hotel, Atlanta, August, 2005 |
|
The existing roofing system was a 16 year old 8000 ft2 EPDM
fully adhered membrane roof. Constant maintenance and repairs
had been completed over the life span of this system. Numerous
leaks into the structure had frustrated the management and
prime rental rooms were unable to earn revenue because of
water damages, falling drywall and the odd odor of mildew.
It was determined that bad flashing details, splitting seams and
screws from the mechanical attachment of the 1" ISO insulation
were backing out and popping through the EPDM membrane
|
 |
| X-Shield FS450 - Big Springs Fish Hatchery |
|
|
| Montana, USA, March, 2005 |
|
The existing concrete substrate was painted with a lead based
paint that was flaking and delaminating. There were also traces
of PCB contamination in the concrete. The fish hatchery was located
up stream of a heavily fished spring which presented the
danger of contamination to both fish and wild life in addition to
local residents. There were also numerous cracks in the concrete.
A total of 52,000 ft2 of concrete need to be coated. After
the lead paint was safely removed the Engineer required a coating
that would form a dense barrier to the contaminated concrete
and also have the ability to accommodate the cracked concrete.
A key factor was also that the coating had to be no toxic to fish
and wildlife.
|
 |
| Sheikh Khalifa Stadium |
|
|
| Sheikh Khalifa Stadium, Qatar |
|
Due to the complexity of the cladding design many of the
gutters were unsuitable for the specified
Hypalon ® sheet membrane to be used as it
requires to be cut, welded and glued. In addition
the gutters had many penetrations. The cladding
sub contractor required a fast cure liquid membrane as many other trades were on the roof
and we jumping in and out of the gutter. This traffic would damage a conventional liquid
membrane as it would need more than 24 hours to cure.
|
 |
| Airport Hanger Gutter Waterproofing |
|
|
| Airbus A380 Hangers Dubai International Airport |
|
A concealed aluminum gutter system was used on
these structures to channel away rain water. The joints
were simple overlaps riveted together. Minor leakage
through the joint was acceptable as rain in Dubai is infrequent
and the gutters would drain the water away
quickly. The problem was with dealing with the early
morning condensation which created an unforeseen
volume of water. The gutter design was not able drain
away this amount of water quickly resulting in almost
daily leakage of water
through the joints.
|
 |
| Generator Grouting |
|
|
| Sharjah Electricity and Water Authority |
|
In order to cope with increased electricity
demand during the summer months when
temperatures can reach 45oC (113oF) The
Government of Sharjah in the United Arab
Emirates is investing in dual fired State of the
Art high efficiency generators developed by
Rolls Royce. They have recently purchased two
30 MW units powered by the same fuel
efficient jet engine as fitted the Boeing 777.
|
 |
| Ready-mix fiber reinforced floor screed at Crowne Plaza Hotel |
|
|
| Dubai Festival City, Dubai |
|
The Al Bahara Ball Room was to be the Crowne Plaza
Hotel's opportunity to entertain Dubai's elite. The floor
screed had to be sufficiently level to carpet, structurally
sound to cope with the heavy movement expected and
also hold many service conduits that would carry the
electrics to leading edge multi media equipment.
|
 |
| Sealing of Barbecue area at Wild Wadi Water Park |
|
|
| Wild Wadi Water Park, Dubai |
|
During the 2007 renovation
of the park, a new barbecue
area was installed. To avoid
oil and fat from the
barbecue staining the stone
facades and floors, X-Shield
StainBlock Sealer was
applied. Using low pressure
spray equipment the sealer
was applied in the late
evening and was open for
use the following morning.
|
 |